| Finalizing Schedule, Cost and Personnel |
|
|
|
|
So far, the project manager has a first guess about duration, cost, and personnel and other resources required for the project and a preliminary project schedule. The next step is to combine these and prove if the project schedule can be accomplished with the available resources. Before you proceed, please read chapter 5, pp. 235-249, of the textbook (Wysocki 2009). The current project schedule defines the schedule for each activity. Each activity has to be performed within a defined schedule: between earliest start date (ES) and latest finish date (LF). But this is a preliminary assumption, not taking into consideration the available resources in terms of personnel. The following examples might happen:
Therefore, the available resources in terms of personnel have to be leveled. Wysocki (2009) suggests strategies for leveling resources:
However, resource leveling has an impact on the costs. Obviously engaging additional personnel will increase the costs, but also other measures, e.g.,
More detailed project planning is required on the micro-level. “Micro” means in this case to break down the activities to the very lowest level and align the activities with concrete persons, dates, responsible persons, descriptions of work, and other information. Wysocki (2009) suggests two templates on the level of the lowest activities (in his termination work packages and tasks):
In order to see other templates, please have a look at the following templates used in the EC project “Bridge-it” (although the work package descriptions are on a higher level): |




